Edinburgh Trams will be late

Thursday, 21 May 2009 01:40
Richard Jeffrey, the Chief Executive of Tie, conceded the tram project would not be completed by July 2011, as originally planned. Hopes they might complete within the £512m budget have also been scuppered.

"We are working as hard as we can to make sure we are up and running as soon as we can - I have a pretty good idea when that will be - but it's not appropriate to announce that while we are still in talks with contractors," said Jeffrey.
Edinburgh Tram
He added: "We're in discussions with contractors at the moment to agree on a revised programme and costs - it wouldn't be sensible to discuss figures."

Source: BBC News